Progress continues toward completion of our new facility in Vung Tau.
Construction and M & E are near completion and fit out is getting underway.

The facility as viewed from the main road.

SEC office building

The workshop viewed from the main door. Roof has been completed, cranes fully installed. Try out and commissioning of cranes and compressor and air delivery system has been completed.

Electrical distribution point, fumes extraction system, emergency eyewash, shower and fire fighting equipment in workshop.

Compressor with air dryer and tank.

The workshop, viewed from the ground and 5th level office.